The Naples Pier is expected back in July 2027. It will sit at least three feet higher than the old one, on fewer and thicker pilings, and the only food at the end of the walk may be ice cream and water from a cart on the land side. The city has rebuilt this pier after hurricanes in 1910, 1926, 1944 and 1960, rebuilt it again in 2015, and then patched it after Irma in 2017. This rebuild changes more than the others did. The new pier is built for walking out, looking at the water, and walking back.
Old Naples has already been living that way for nine months. Since early January, 12th Avenue South has ended at a construction fence, and beach trips have gone around it.
Where the Concrete Stands This Week
Shoreline Foundation, Inc. took over the site the day after the January 5 groundbreaking. City Council had awarded the company a $23.5 million construction contract back in October 2024. The City's own timeline for 2026 reads like this:
- January 6: Construction begins.
- April 13: Demolition of the old pier is complete.
- May 5: Divers begin a month of debris removal, including pilings from the 1990s buried in the sand.
- June 17: Crews start building a trestle along the south side so work can continue when weather sends the offshore barges to shelter.
- June 26: First concrete pour, about 20 yards of a total of roughly 602.
- July 24: About 200 cubic yards poured, and two-thirds of the new decking delivered.
- September 18: The mid-pavilion pour pushes the project past the halfway point for concrete.
The decking is ipe, a tropical hardwood known for resisting rot. The City says it won't be laid until all the concrete is in. Once the planks start going down, the pier will start to look like a pier again from the beach.
Naples Daily News reported on October 1 that the project is on a 14-to-18-month schedule, with completion expected in July 2027 and the public back on the pier sometime around the middle of next year. That puts the reopening after this coming season, so the 2026-27 winter will be the second one without a pier. The same report puts the total cost at $26 million. FEMA's $11.4 million grant came through last December after about three years of waiting. The City's rebuild page posts each milestone as it happens. The live Pier Cam at NaplesPanorama.org still shows sunsets over the work site.
Why the Pier Is Higher and Its Pilings Fewer
Hurricane Ian badly damaged about 460 feet of the old pier in September 2022, and roughly 140 feet of the end ended up on the floor of the Gulf. The waves gutted the concession, shelter and storage buildings at the midpoint. The City's engineers concluded that most of the structure was compromised and had to be replaced.
The new design answers that damage directly. The deck goes up at least three feet. The pilings are larger in cross-section but fewer in number and spaced farther apart, which the City says reduces the pier's effect on the shoreline on either side. The concrete under the ipe deck is also heavier. Turrell, Hall & Associates leads the architecture and engineering work in partnership with MHK Architecture.
What Council Took Off the Land Side
The decision Old Naples will notice most on reopening day was made on land. At the March 4, 2026 meeting, City staff presented the version council members had agreed on at a June 16, 2025 workshop. It calls for less covered area, limited covered seating on the south side, a proposed history wall, and showers moved out from under the shade. The updated drawings take out the concession area completely and cut back the shade on the south side substantially.
For years, that concession was Cosmo's at the Pier, owned by Gianluca Corso, who also owns Cosmo's Cafe & Pizzeria. Gulfshore Business reports that the pier has had concessions since 1946 and that Cosmos leased the restaurant space starting in 2015. Naples Daily News summed up council's position in March: no burgers or beer at the new pier, but possibly ice cream and water. Council kept its decision against a concession stand and agreed to allow portable carts on the land side with a shorter menu. Gulfshore Business reported that the cart under consideration would sell water, ice cream and soda, with electrical service on the land side. The city manager told council a food truck wouldn't fit and a cart was the only option. No cart operator has been named publicly.
When WINK News covered the debate, one Naples resident said she used to walk the pier every week and brought her own food, and that a concession mattered more to visitors who don't know the area. The finished pier is built around that kind of visit.
What the New Pier Adds Instead
The space the concession gave up goes mostly to watching the water and keeping the beach running. On the north side, a much smaller building keeps the storage space and adds a Naples Police Department substation with an accessible restroom. Its office has a turtle-safe glass observation window and a desk for monitoring cameras. Gulfshore Business reported that the approved plan also includes public restrooms with a family restroom, a beach patrol office, and an underwater camera so visitors can see the marine life below the deck. The City's approved design renderings show a ramp leading up to an end pavilion. The City says the design is meant to give visitors more ways to use the pier without getting in the way of anglers.
The City counted more than one million visits a year to the old pier, for fishing, socializing, wildlife watching, exercise and the concession. The new design keeps all of those uses except the last one.
The Beach Ends Covering for the Pier This Season
Until the pier reopens, the pier itself, its stairs, restrooms and showers, and 12th Avenue South west of Gulf Shore Boulevard South are all closed. The pier parking lot at 12th Avenue South and Gulf Shore Boulevard South is mostly fenced off for construction, with only its western third open to the public. The City has set up pedestrian bypasses at the two beach ends on either side, Broad Avenue South and 13th Avenue South, and says both will stay open, with restrooms, for the rest of the project.
The City's beach access table showed this status for the Old Naples stretch at the time of this research:
| Beach access | Status |
|---|---|
| 1st through 11th Avenue South | Open |
| Broad Avenue South | Open, restrooms available |
| 12th Avenue South | Closed for the pier rebuild |
| 13th Avenue South | Open, restrooms available |
| 14th through 18th Avenue South | Open |
| 2nd, 3rd, 4th and 8th Avenue North | Closed for the Stormwater Beach Outfall Project |
| Lowdermilk Park | Open |
The City updates that table as projects move, so the public beach access page is worth checking before a weekend morning. Farther north, Lowdermilk Park has restrooms, showers, ADA beach mats, benches and gazebos.
The Old Naples Association has already been holding its sunset events away from the pier. It lists Sunday Beach Sunset Cocktails among its seasonal programs, and it held its 2026 Sunset Beach Party at the 7th Avenue South beach end on March 22. Its next listed event is on land. On Tuesday, November 10, the association hosts a coffee with Mayor Teresa Heitmann at Ridgway Bar & Grill.
Where the Old Pier Went
Most of the old pier now sits in the Gulf. On April 24, crews dropped 59 concrete pilings from the demolished structure at Wasmer Reef, about 10 miles off Gordon Pass. The pilings weigh 300 tons combined. They expand an artificial reef first set down in 2015 that already has coral and aquatic vegetation and gives young and adult fish shelter and food. The reef can only be reached by boat. For anyone who used to fish off the pier and now has a reason to head out through Gordon Pass, our guide to where to fish near Naples covers other options.
The next big change at the site will be the ipe decking, which goes down once the last concrete is poured. The Old Naples neighborhood guide covers the streets between the beach ends and Third Street South.